Hello,
I’m a new user of Duplicate. My question is about how to delete or adjust a backup task?
For example:
I want to to change the date or time of a scheduled task
I want to change the source of the data in a backup task.
Thanks
Jack
Hello,
I’m a new user of Duplicate. My question is about how to delete or adjust a backup task?
For example:
I want to to change the date or time of a scheduled task
I want to change the source of the data in a backup task.
Thanks
Jack
In the GUI you click on your backup:
and then “Configutation - edit”. Then tab (4) Schedule
Click on Next or Tab (5) and then “Save”
Same for question 2. But in that case Tab (3) “Source Data”.
But keep in mind: If you change the source data, the already backuped data will remain in you backup! So this is fine, if you extend the source, but if you really change the source you have to manually purge the old data or delete the old versions.